|
| | HB3523 Engrossed | - 2 - | LRB099 09392 MLM 29599 b |
|
|
1 | | Act.
|
2 | | "Commercial wind energy facility" means a wind energy |
3 | | conversion facility of equal or greater than 500 kilowatts in |
4 | | total nameplate generating capacity. "Commercial wind energy |
5 | | facility" includes a wind energy conversion facility seeking an |
6 | | extension of a permit to construct granted by a county or |
7 | | municipality before the effective date of this Act. "Commercial |
8 | | wind energy facility" does not include a wind energy conversion |
9 | | facility: (1) that has submitted a complete permit application |
10 | | to a county or municipality and for which the hearing on the |
11 | | completed application has commenced on the date provided in the |
12 | | public hearing notice, which must be before the effective date |
13 | | of this Act; (2) for which a permit to construct has been |
14 | | issued before the effective date of this Act; or (3) that was |
15 | | constructed before the effective date of this Act. |
16 | | "Commercial wind energy facility owner" means a private |
17 | | commercial enterprise that owns or operates a commercial wind |
18 | | energy facility.
|
19 | | "Construction" means the installation, preparation for |
20 | | installation, or repair of a commercial wind energy facility.
|
21 | | "County" means the county where the commercial wind energy |
22 | | facility is located.
|
23 | | "Deconstruction" means the removal of a commercial wind |
24 | | energy facility from the property of a landowner and the |
25 | | restoration of that property as provided in the agricultural |
26 | | impact mitigation agreement.
|
|
| | HB3523 Engrossed | - 3 - | LRB099 09392 MLM 29599 b |
|
|
1 | | "Department" means the Department of Agriculture.
|
2 | | "Landowner" means any person (1) with an ownership interest |
3 | | in property that is used for agricultural purposes and (2) that |
4 | | is a party to an underlying agreement.
|
5 | | "Underlying agreement" means the written agreement with a |
6 | | landowner, including, but not limited to, an easement, option, |
7 | | lease, or license, under the terms of which another person has |
8 | | constructed, constructs, or intends to construct a commercial |
9 | | wind energy facility on the property of the landowner.
|
10 | | Section 15. Agricultural impact mitigation agreement.
|
11 | | (a) A commercial wind energy facility owner of a commercial |
12 | | wind energy facility located on landowner property shall enter |
13 | | into an agricultural impact mitigation agreement with the |
14 | | Department outlining construction and deconstruction standards |
15 | | and policies designed to preserve the integrity of any |
16 | | agricultural land that is impacted by commercial wind energy |
17 | | facility construction and deconstruction.
|
18 | | (b) The agricultural impact mitigation agreement shall |
19 | | include, but is not limited to, such items as restoration of |
20 | | agricultural land affected by construction, deconstruction |
21 | | (including upon abandonment), construction staging, and |
22 | | storage areas; support structures; aboveground facilities; guy |
23 | | wires and anchors; underground cabling depth; topsoil |
24 | | replacement; protection and repair of agricultural drainage |
25 | | tiles; rock removal; repair of compaction and rutting; land |
|
| | HB3523 Engrossed | - 4 - | LRB099 09392 MLM 29599 b |
|
|
1 | | leveling; prevention of soil erosion; repair of damaged soil |
2 | | conservation practices; compensation for damages to private |
3 | | property; clearing of trees and brush; interference with |
4 | | irrigation systems; access roads; weed control; pumping of |
5 | | water from open excavations; advance notice of access to |
6 | | private property; indemnification of landowners; and |
7 | | deconstruction plans and financial assurance for |
8 | | deconstruction (including upon abandonment).
|
9 | | (c) For commercial wind energy facility owners seeking a |
10 | | permit from a county or municipality for the construction of a |
11 | | commercial wind energy facility, the agricultural impact |
12 | | mitigation agreement shall be entered into prior to the public |
13 | | hearing required prior to a siting decision of a county or |
14 | | municipality regarding the commercial wind energy facility. |
15 | | The agricultural impact mitigation agreement is binding on any |
16 | | subsequent commercial wind energy facility owner that takes |
17 | | ownership of the commercial wind energy facility that is the |
18 | | subject of the agreement.
|
19 | | (d) If a commercial wind energy facility owner seeks an |
20 | | extension of a permit granted by a county or municipality for |
21 | | the construction of a commercial wind energy facility prior to |
22 | | the effective date of this Act, the agricultural impact |
23 | | mitigation agreement shall be entered into prior to a decision |
24 | | by the county or municipality to grant the permit extension.
|
25 | | (e) The Department shall adopt rules that are necessary and |
26 | | appropriate for the implementation and administration of |
|
| | HB3523 Engrossed | - 5 - | LRB099 09392 MLM 29599 b |
|
|
1 | | agricultural impact mitigation agreements as required under |
2 | | this Act.
|
3 | | Section 90. The Counties Code is amended by changing |
4 | | Section 5-12020 as follows:
|
5 | | (55 ILCS 5/5-12020) |
6 | | Sec. 5-12020. Wind farms. A county may establish standards |
7 | | for wind farms and electric-generating wind devices. The |
8 | | standards may include, without limitation, the height of the |
9 | | devices and the number of devices that may be located within a |
10 | | geographic area. A county may also regulate the siting of wind |
11 | | farms and electric-generating wind devices in unincorporated |
12 | | areas of the county outside of the zoning jurisdiction of a |
13 | | municipality and the 1.5 mile radius surrounding the zoning |
14 | | jurisdiction of a municipality. There shall be at least one |
15 | | public hearing not more than 30 days prior to a siting decision |
16 | | by the county board. Notice of the hearing shall be published |
17 | | in a newspaper of general circulation in the county. A |
18 | | commercial wind energy facility owner, as defined in the Wind |
19 | | Energy Facilities Agricultural Impact Mitigation Act, must |
20 | | enter into an agricultural impact mitigation agreement with the |
21 | | Department of Agriculture prior to the date of the required |
22 | | public hearing. A commercial wind energy facility owner seeking |
23 | | an extension of a permit granted by a county prior to the |
24 | | effective date of this amendatory Act of the 99th General |
|
| | HB3523 Engrossed | - 6 - | LRB099 09392 MLM 29599 b |
|
|
1 | | Assembly must enter into an agricultural impact mitigation |
2 | | agreement with the Department of Agriculture prior to a |
3 | | decision by the county to grant the permit extension. Counties |
4 | | may allow test wind towers to be sited without formal approval |
5 | | by the county board. Any provision of a county zoning ordinance |
6 | | pertaining to wind farms that is in effect before the effective |
7 | | date of this amendatory Act of the 95th General Assembly may |
8 | | continue in effect notwithstanding any requirements of this |
9 | | Section. |
10 | | A county may not require a wind tower or other renewable |
11 | | energy system that is used exclusively by an end user to be |
12 | | setback more than 1.1 times the height of the renewable energy |
13 | | system from the end user's property line.
|
14 | | (Source: P.A. 95-203, eff. 8-16-07; 96-306, eff. 1-1-10; |
15 | | 96-566, eff. 8-18-09; 96-1000, eff. 7-2-10.)
|
16 | | Section 95. The Illinois Municipal Code is amended by |
17 | | changing Section 11-13-26 as follows:
|
18 | | (65 ILCS 5/11-13-26) |
19 | | Sec. 11-13-26. Wind farms. |
20 | | (a) A municipality may regulate wind farms and |
21 | | electric-generating wind devices within its zoning |
22 | | jurisdiction and within the 1.5 mile radius surrounding its |
23 | | zoning jurisdiction. There shall be at least one public hearing |
24 | | not more than 30 days prior to a siting decision by the |
|
| | HB3523 Engrossed | - 7 - | LRB099 09392 MLM 29599 b |
|
|
1 | | corporate authorities of a municipality. Notice of the hearing |
2 | | shall be published in a newspaper of general circulation in the |
3 | | municipality. A commercial wind energy facility owner, as |
4 | | defined in the Wind Energy Facilities Agricultural Impact |
5 | | Mitigation Act, must enter into an agricultural impact |
6 | | mitigation agreement with the Department of Agriculture prior |
7 | | to the date of the required public hearing. A commercial wind |
8 | | energy facility owner seeking an extension of a permit granted |
9 | | by a municipality prior to the effective date of this |
10 | | amendatory Act of the 99th General Assembly must enter into an |
11 | | agricultural impact mitigation agreement with the Department |
12 | | of Agriculture prior to a decision by the municipality to grant |
13 | | the permit extension. A municipality may allow test wind towers |
14 | | to be sited without formal approval by the corporate |
15 | | authorities of the municipality. Test wind towers must be |
16 | | dismantled within 3 years of installation. For the purposes of |
17 | | this Section, "test wind towers" are wind towers that are |
18 | | designed solely to collect wind generation data.
|
19 | | (b) A municipality may not require a wind tower or other |
20 | | renewable energy system that is used exclusively by an end user |
21 | | to be setback more than 1.1 times the height of the renewable |
22 | | energy system from the end user's property line. A setback |
23 | | requirement imposed by a municipality on a renewable energy |
24 | | system may not be more restrictive than as provided under this |
25 | | subsection. This subsection is a limitation of home rule powers |
26 | | and functions under subsection (i) of Section 6 of Article VII |